Illustrative image – not actual.Dispute over land has forced North Eastern Electric Power Corpn. to stall work on its 2x30 MW Tuirial hydel power project. The hydel plant was to come up on the river Tuirial, a tributary of the river Basak, in Aizawl district along the border of Cachar district of Assam.
The project involves the construction of a 77 mtrs high homogenous earthfill dam. The water conductor system comprises a headrace tunnel of 109.5 mtrs length and a 3.8 mtrs dia surface penstock of 176 mtrs length finally bifurcating to 2.7 mtrs dia near the power house which will accommodate 2 hydel sets of 30 MW each.