The production from Utkal-E coal block at Angul in Orissa allotted to Tata Sponge Iron Ltd (TSIL) may be delayed due to land acquisition problems.
According to sources, the coal mine project requires about 1,000 ha of which 600 ha is private land. Of the remaining 400 ha, 200 ha are forest land while the rest 200 ha is government land under the Chhendipada tehsil. The government land is yet to be handed over to the company for the Rs 500 crore coal mine project, though the state government had earlier signed an MoU with TSIL. The coal mine project was being taken up by TSIL in association with two other private players- Scaw Industries of Dhenkanal and SPS Sponge Iron of Sundergarh.
Coal production from this block is now likely to resume only in early 2011 instead of the current year.