TSGENCO to conduct boiler light up test for KTPS Unit-12Illustrative image – not actual.
The Telangana Power Generation Corporation (TSGENCO) is preparing to conduct the boiler light up test for the 800 MW supercritical unit by the end of December 2017.

The unit under construction is located at the Kothagudem Thermal Power Station (KTPS) in Palvancha town in Bhadradri district of Telangana.

Work on the KTPS’s Unit-12 (1x800 MW) under Stage-VII has reached the final stage.

So far, 80 percent of the work has been completed and the remaining work relating to the coal plant, crusher unit and conveyor and other main components of the plant are expected to be completed in a few weeks.

Unit-11 of the KTPS was commissioned in 2011 as part of the capacity addition programme, raising the installed capacity of the KTPS to 1,720 MW.

Unit-12 will be synchronised with the power grid and commercial operation will be kickstarted by early 2018.

A generator weighing 480 tonne is expected to arrive at the KTPS complex from the Krishnapatnam port in Andhra Pradesh in a few days.