Trouble brews for R-Power's Krishnapatnam projectIllustrative image – not actual.

Reliance Power's (R-Power) 4,000-MW Krishnapatnam ultra mega power project (UMPP) in Andhra Pradesh is facing problems owing to various reasons.

One of the main issues is a recent change in Indonesian law which mandates all parties to sell coal at market prices. Earlier, Indonesian coal mines had the freedom to bilaterally agree coal prices with buyers. The latest change in law will impact the viability of this project as well as others that are based on imported coal, especially from Indonesia.

Other problems troubling the Krishnapatnam UMPP include the condition of the soil where the foundation for the boiler has to be laid and land disputes at strategic locations. Work on boiler foundation has not yet started. So far, R-Power has completed 90 per cent boundary work and, soil investigations for sea water intake systems are underway.