Triveni plans three new sugar unitsIllustrative image – not actual.

Triveni Engineering & Industries plans to set up three new sugar plants and expand its existing factories. The company would commission a new sugar mill, with capacity 5,000-7,000 tccpd at Sabitgarh in Bulandshar district by October 2005. The Sabitgarh mill's capacity could be expanded further to 10,000-12,000 tccpd.

The company has earmarked Rs.500 crore over a three-year period starting April 2004 for its plans that include greenfield and brownfield options. The company so far spent Rs.125 crore.

 Triveni would also increase the capacity of its Khatauli sugar mill from 11,750 tcd to 16,000 tcd by October 2005. The Khatauli unit would also have power co-generation plant of 23 MW. Additionally, the company would commission two new units in western Uttar Pradesh with 5,000-7,000 tcd in 2006-07 sugar season.

During the 2004-05 sugar season (October-September), Triveni produced 38.14 lakh bags or 38.1 lakh tonnes.