Triveni Engineering plans Rs.558 crore expansionIllustrative image – not actual.

The board of Triveni Engineering on 1 April 2006 approved an overall investment programme costing Rs.558 crore.

The expansion plan includes:

  • Setting up of two new sugar units of around 6,000 tccpd each at Chandanpur and Rani Nagal in Uttar Pradesh and expansion of its existing Ramkola sugar unit capacity from 3,500 tccpd to 6500 tccpd.
  • Setting up of additional cogeneration facilities of 22 MW at Khatauli, Uttar Pradesh
  • Setting up of a distillery of 160 kilo ltrs, per day capacity; and
  • Expansion of turbine manufacturing capacity and installation of a full speed vacuum balancing machine

The expansion programme will be financed largely through equity. The board approved the raising of up to Rs.550 crore through floatation of equity and equity-linked instrument in the domestic and international market. Shareholders' approval to this proposal will be sought on 28 April 2006.