Illustrative image – not actual.ONGC Tripura Power Co, a special purpose vehicle formed by ONGC, Infrastructure Leasing & Financial Services and Tripura government, has extended submission of bids for engineering, procurement and construction to November 2007 for a proposed 740 MW gas-based power project at Pallatana in Tripura.
According to the original plan, the last date for submission of bids was 14 August 2007. However the deadline has been extended so that more national and international players can participate in the bidding process.
The ONGC board has accorded investment approval of Rs.576.63 crore for a total project cost of Rs.3,844.17 crore based on the debt-equity ratio of 70:30 and ONGC's equity contribution of 50 per cent of OTPC. The entire project is scheduled for completion by 2011.
Also See:
ONGC's Tripura power plant to commission by 2011 (15-May-07)
Related Links:
Project profile