Trials on Peenya corridor to commence on 10 June 2013Illustrative image – not actual.

Bangalore Metro Rail Corporation (BMRC) is likely to commence trial run on the Peenya-Sriramapuram stretch of Namma Metro's northern line from 10 June 2013.

 

The trial run will be extended up to Sampige Road Metro Station by 8 July. The trials will allow the rakes to run up to their full speed of 80 kmph, thereby testing track strength and distance brake systems of the rakes.

 

The Peenya-Sampige Road line was slated to begin operations in mid-2013, but was delayed on various issues. The 9.9 km Peenya-Sampige Road stretch consists of Reach 3 (Yeshwantpur-Sampige Road) and Reach 3A (Peenya-Yeshwantpur). There will be 10 stations on the stretch. Work is afoot on further extension on this corridor - Reach 3B - between Peenya and Hesaraghatta.

 

Namma Metro is still awaiting two more technical clearances at the Peenya depot, including one on exemption from provision of check rails, which are used in curves. However, until the check rail clearance is received, BMRC can't begin oscillation trials between Peenya depot and Sampige Road stations. The approvals are expected to be obtained from Railway Design and Standards organization (RDSO), Lucknow. BMRC has sent proposals to the Railway Board through the commissioner of railway safety.

 

As far as civil work is concerned, around 78 per cent is over in Yeshwantpur, Soap Factory, and Mahalakshmi Layout stations, while 74 per cent has been completed in Rajajinagar, Kuvempu Road and Srirampuram stations. Granite flooring, and electrical and mechanical fittings are underway. Spans totalling up to a length of 66 mtr have been laid over railway lines at Srirampuram. However, three spans between six piers are yet to be laid between Yeshwantpur and Peenya.

 