Illustrative image – not actual.The trial runs on the Yamuna Bank-New Ashok Nagar Section of the Delhi Metro have begun on 25 July 2009. The trial run will take place upto New Ashok Nagar for the first 10 days and subsequently the entire section upto Noida City Centre will be covered.
The trial runs are likely to go on for a month's time, during which the section will be tested for signalling, tracks, telecommunication, interfacing of train working with different systems and OHE supply.
The interim stations on the section are Akshardham, Mayur Vihar Phase-I and Mayur Vihar Extension and the section is fully elevated.
The Yamuna Bank to Noida section is slated to be opened for the public by end-August 2009 and with the opening of this section Line-III will comprise of a total of 42 stations and its length will increase to 47.2 km.
Also See:
Trial run begins on Delhi Metro's phase II main line (23-May-09)
Related Links:
Project profile