Illustrative image – not actual.DMRC on 16 July 2010 commenced trial runs on the Central Secretariat-Qutub Minar corridor which is to be integrated with the Gurgaon line.
Trial runs on the 12.53 km-long corridor are likely to continue for at least four weeks till the line is integrated with the 14.47 Qutub Minar-Gurgaon line, which was thrown open in June 2010. During the trial runs, the interaction of the metro train with physical infringements (civil structure) is to be checked to ensure that there is no physical blockage during the movement of the train on the track.
Besides, the entire signalling system is likely to be tested. The response of the train at different speeds, braking of the train and the interconnection with the Operations Control Centre is also to be monitored during the trials.
The trial runs are likely to continue for a few weeks and the corridor is expected to be opened for the public in August 2010 after attaining the statutory safety clearances.
Once the entire Metro corridor is thrown open, passengers can hope to reach Gurgaon in about 52 minutes from Connaught Place. Ultimately, it is to be attached to the existing Jahangirpuri-Central Secretariat line and the entire distance of around 42 km will be covered in less than 90 minutes.
The Central Secretariat-Qutub Minar corridor has 10 stations and the entire stretch is underground.