Trial run on 20 km route of Mumbai Metro 2A and 7 soonIllustrative image – not actual.
The Mumbai Metropolitan Region Development Authority (MMRDA) has achieved a major milestone in the overhead cable work of Metro Line 2A (Dahisar to DN Nagar) and Metro Line 7 (Dahisar East to Andheri East) work. 
 
The chief electrical inspector of the government of India (CEIG) did inspection of overhead equipment (OHE) line of Metro Line 2A successfully for the section from Dahisar to Kamraj Nagar on 24 May 2021.  
 
Due to the prevailing pandemic situation and travel restrictions, MMRDA shared updates to the inspection officer using digital platform so the proposed plan of Metro Trial run could be achieved. 
 
The charging OHE on the Metro line would be done on 25 May 2021. Thereafter, the proposed 20 km trial run (Aarey to Kamraj Nagar) will commence. 
 
The OHE line charging on Metro Line 7 (Aarey to Dahisar) has been completed successfully, after receiving the required approval from CEIG. 
 
MMRDA has successfully managed to complete the work on the 20 km stretch despite COVID-19. 
 
In initial phase, the authority will carry out trial run between Aarey and Kamraj Nagar on Metro 2A and 7 and later as work of the remaining section is completed the distance of trial runs will be expanded.