Illustrative image – not actual.A 67-km-long high voltage 400 kV transmission line constructed between Kothagudem and Khammam in Andhra Pradesh was commissioned on 7 March 2011.
The line was constructed by the Transmission Corporation of Andhra Pradesh at a cost of Rs 150 crore to evacuate power from APGENCOs Kothagudem Thermal Power Station Stage VI. The new transmission line, which is connected to the substation of PGCIL at Khammam, is expected to improve the voltage of the power supplied to end-users in Telangana region.
A total of three 400 kV double circuit evacuation transmission lines will now be implemented between Krishnapatnam and Manubrolu in Nellore district (36 km); between Krishnapatnam and Chittoor (188 km), and between the Singareni Collieries Thermal Power Station in Adilabad district to Gajwel in Medak district (165 km).