Illustrative image – not actual.Tractebel Energy has pulled out of Jindal Tractebel
Power Company Ltd (JTPCL), which operates the 260 MW Vijayanagar power plant at
Toranagallu in the Bellary district of Karnataka.
JTPCL was the 50:50 joint venture between Tractebel
and Jindal Vijayanagar Steel Ltd (JVSL). The joint venture was planning to
expand the capacity of the power plant from the existing 260 MW to 760 MW in
two phases of 250 MW each.
Tractebel’s stake of 15.75 crore shares in JTPCL, has
been valued at Rs.242 crore (i.e. $50.5 million). This means that each share
has been priced at around Rs.15.40. JTPCL's board has reportedly cleared the
deal.
The Jindals would be picking up 12 per cent of
Tractebel’s equity, while financial institutions, viz. IDBI and ICICI would
reportedly be picking 19 per cent each. However, this stake that would be held
by the FIs could be bought back by the Jindals in the future at a predetermined
pricing formula, or could be passed on to another joint venture partner.
Tractebel has been
attempting to exit from the joint venture since 2000. But, attempts last
year were thwarted by pricing issues. Earlier, the Jindals and the FIs had
together valued Tractebel’s stake at $42 million, which was unacceptable to it.
Tractebel has major interests in both generation and
distribution in the US and European markets. In Belgium, it has major interests
in the distribution business through its associate company, Electrabel. Both
Tractebel and Electrabel are part of the French utilities giant, Suez Lyonnaise
des Eaux.
Meanwhile, Mirant Corporation,
Reliance Power’s joint venture partner for the Hirma Power project has also quit
the project.