Tata Power Delhi Distribution (Tata Power-DDL) has commissioned a 66/11 kV AIS grid substation at Siraspur in Delhi, on 14 February, 2017.
The total expenditure on the project is Rs 38 crore. The grid substation has been constructed on 4,300 sq mtr.
The unmanned grid substation has an installed capacity of 50 MVA, with 16 outgoing feeders at 11 kV level. It will be remotely operated from Tata PPDDL’s Supervisory Controlled and Data Acquisition Centre (SCADA).
It has an incoming supply from two 66 kV underground cable circuits emanating from two lines from 66 kV TPDDL Badli grid and two 66 kV cable lines from upcoming 220 kV DTL grid at SGTN.