Torrent Power receives LOA for Rs 1,825-cr RE project Illustrative image – not actual.

Torrent Power has received a letter of award (LoA) for setting up a 150 MW wind solar hybrid project with an investment of Rs 1,825 crore.

The company has received LoA from its distribution unit for the grid-connected project under greenshoe option. The renewable energy project will supply power at a tariff of Rs 3.65 per kWh, and will be commissioned within 24 months from the signing of power purchase agreement (PPA).

The contract will be for 25 years from the commissioning of the project.

The annual capacity utilisation factor (CUF) will not be less than 50 percent for any year during the term of the PPA and rated power capacity of wind and solar will be in the ratio of 2:1. To meet this, the company plans to install 245 MW of wind and solar capacity projects against a contracted capacity of 150 MW.