Illustrative image – not actual.The implementation of the Tobruk power generation plant project in Tobruk on Libya’s eastern Mediterranean coast, near the border with Egypt, has been relaunched.
The works have been restarted after approximately three years of delay.
The country is however gradually returning to normal and as a result, the General Electricity Company of Libya (GECOL) has enacted the Letter of Credit towards METKA, a subsidiary of MYTILINEOS, giving green light for construction of the plant.
The project, which involves supply and installation of four General Electric GT13E2 gas turbines in open cycle configuration, together with all associated balance of plant equipment and the construction of a 220/66 kV substation, will be implemented in three stages.
The first stage will be construction of the first turbine that will be able to directly reinforce the country’s energy system by almost 160 MW.
Once all three stages are finalised, the plant will have a total power output capacity of more than 650 MW and it will also have dual fuel (natural gas or distillate fuel oil) ability.
The contract for the implementation of the project is valued at USD 400 million.
The project will offer an immediate solution that will enable the country to invest in its productive reconstruction, while in the long run it will help Libya acquire a state-of-the-art power generation plant that will cover vital and pressing needs in the project’s broader region.
The works have been restarted after approximately three years of delay.
The country is however gradually returning to normal and as a result, the General Electricity Company of Libya (GECOL) has enacted the Letter of Credit towards METKA, a subsidiary of MYTILINEOS, giving green light for construction of the plant.
The project, which involves supply and installation of four General Electric GT13E2 gas turbines in open cycle configuration, together with all associated balance of plant equipment and the construction of a 220/66 kV substation, will be implemented in three stages.
The first stage will be construction of the first turbine that will be able to directly reinforce the country’s energy system by almost 160 MW.
Once all three stages are finalised, the plant will have a total power output capacity of more than 650 MW and it will also have dual fuel (natural gas or distillate fuel oil) ability.
The contract for the implementation of the project is valued at USD 400 million.
The project will offer an immediate solution that will enable the country to invest in its productive reconstruction, while in the long run it will help Libya acquire a state-of-the-art power generation plant that will cover vital and pressing needs in the project’s broader region.