Illustrative image – not actual.BSES’ plan to set up a 250 MW power plant Srimushanam in Tamil Nadu has been affected, with the Tamil Nadu Electricity Board (TNEB) withdrawing the clearance given to the project, under section 44 of the Electricity Supply Act. This clearance is necessary for setting up a power project in the state.
TNEB withdrew the clearance, since
it felt that there were too many projects coming up in the state and the Srimushanam
project was not required.
The Srimushanam project is proposed
to be set up by Tamil Nadu Industries Captive Power Company Ltd, a 51:49 joint venture
between BSES and a group of textile exporters from Tirupur.
BSES has challenged TNEB’s decision
in the Chennai High Court. BSES is planning to double the capacity of the project
to 500 MW, subject to the High Court clearance. It is in talks with Power Trading
Corporation for the offtake of power from the project, which has been in limbo
for over four years.