The Tamil Nadu Electricity Board (TNEB) plans to take up two major power generation projects - 500 MW Kundah pumped storage hydel power project and the 600 MW Ennore Thermal Power Station (ETPS) Annex 1x600 MW - by March 2011 in Tamil Nadu.

The Rs 1,108-crore Kundah project comprises four units of 125 MW each. The project is to be implemented in two phases. In the Phase I, TNEB proposes to set up one unit of 125 MW at a cost of Rs 488 crore. The Phase II is likely to consist of the other three units and is estimated to cost Rs 620 crore. The project is being funded by REC.

On 21 July 2010, TNEB and REC discussed the projects of TNEB that are covered by an MoU signed by the two organisations in 2007. The MoU makes way for Rs 16,000 crore of REC funding of various projects in the state.

For the 600 MW ETPS Annex 1x600 MW, the DPR is reportedly underway. The Rs 3,093-crore project is to be funded by a Rs 2,475 crore loan from REC. The project is likely to come up within the existing Ennore thermal power station premises.