Tamil Nadu Electricity Board (TNEB) may
reportedly not appoint an arbitrator in response to the international
arbitration proceedings initiated by Videocon Power against TNEB.
Videocon
Power had served an arbitration notice to TNEB for settling the on-going
dispute over the power purchase agreement for its 1050 MW power project in
Tamil Nadu. It may be recalled that TNEB had cancelled the escrow cover granted
to Videocon Power, in favour of other power projects coming up in the State.
As
per the arbitration notice, TNEB has time till 27 December 2000 for appointing
an arbitrator. However, TNEB has reportedly decided against appointing one, and
has preferred to wait for the verdict of the Madras High Court, where the case
proceedings are already underway.