On 30 September 2002, the Tamil Nadu Electricity Board cleared the commissioning of the 18.6 MW captive power plant of Tamil Nadu Petroproducts (TPL).

 

The captive power plant would facilitate the turnaround of the heavy chemicals division. The division, which was taken over from SPIC, another group company, has been making losses due to the high costs of power. The company, which is currently spending Rs.100 crore annually on power, is likely to save approximately Rs10 crore to Rs.15 crore, depending on the cost of the fuel once the captive power plant is fully functional.

 

Commissioning of the captive power plant would also make TPL’s heavy chemicals division self-reliant by providing 11 crore units of electricity of the required 13 crore units every year. The balance 2 crore units being drawn from the company’s wind farms.

  