Illustrative image – not actual.On 15 January 2007, National Highways Authority of India received a cheque of Rs.55.11 crore as negative grant from GMR Ulundurpet Expressways towards 4 laning and strengthening of the existing two laned Tindivanam-Ulunderpet section of NH-45.
This 71.25 km long Tindivanam-Ulunderpet section (KM 121.0 to KM192.25) of NH-45 comes under Phase-II of NHDP and will be taken up on BOT (Toll) basis. The total negative grant for this project is Rs.152.10 crore (NPV discounted at 10 percent) which will be disbursed upto the 13th year of the concession period.
The salient features of the project is given below :
| Name of Concessionaire | GMR Ulundurpet Expressways Private Limited |
| Length of the Project | 71.25 km |
| Total Project Cost | Rs.480 crore |
| Concession Period | 20 years |
| Period of Construction | 30 months |
| Amount of Grant | Rs.152.10 crore disbursed upto 13th year of the Concession Period |
| Date of signing of Concession Agreement | 19 April 2006 |
| Completion | April 2009 |
| Length of Service Road | 21.1 km |
| Bypasses | Tindivanam (5 km), Villupuram (8.6 km) |
| ROBs | 3 nos |
| Grade separator | 3 nos |
| Pedestrian underpasses | 5 nos |
| Bridges | 20 nos |