Tindivanam-Ulunderpet section receives negative grant chequeIllustrative image – not actual.

On 15 January 2007, National Highways Authority of India received a cheque of Rs.55.11 crore as negative grant from GMR Ulundurpet Expressways towards 4 laning and strengthening of the existing two laned Tindivanam-Ulunderpet section of NH-45. 

This 71.25 km long Tindivanam-Ulunderpet section (KM 121.0 to KM192.25) of NH-45 comes under Phase-II of NHDP and will be taken up on BOT (Toll) basis. The total negative grant for this project is Rs.152.10 crore (NPV discounted at 10 percent) which will be disbursed upto the 13th year of the concession period. 

The salient features of the project is given below :

Name of Concessionaire GMR Ulundurpet Expressways Private Limited
Length of the Project 71.25 km
Total Project Cost Rs.480 crore
Concession Period 20 years
Period of Construction 30 months
Amount of Grant Rs.152.10 crore disbursed upto 13th year of the Concession Period
Date of signing of Concession Agreement 19 April 2006
Completion April 2009
Length of Service Road 21.1 km
Bypasses Tindivanam (5 km), Villupuram (8.6 km)
ROBs  3 nos
Grade separator 3 nos
Pedestrian underpasses 5 nos
Bridges 20 nos