Time, cost overruns beset urban development and railway projectsIllustrative image – not actual.

Power, urban development and railways projects are particularly victimized by time and cost overruns, going by information contained in the Annual Report of the Ministry of Statistics & Programme Implementation (MoSPI), for the year 2002-03.

 

As of 1 October 2002, there were 542 public sector projects, each costing at least Rs.20 crore, under the monitor of the MoSPI. Against the latest aggregate approved cost of Rs.192,752 crore, the total anticipated completion cost of these projects stood at Rs.213,134 crore, implying an overall cost escalation of 10.6 per cent.

 

With the lone exception coal projects, wherein 60 projects having total anticipated cost of Rs.10,400 crore indeed lower than the latest approved cost of Rs.10,516 crore, all the other sectors were afflicted by cost escalations. Time overruns, too, seemed to be a ubiquitous phenomenon.

 

There were eight urban development projects totally costing Rs.5,163 crore, at the time of latest approval. These are now expected to have a completion cost of Rs.9,130 crore, translating into a cost escalation of 77 per cent, the highest amongst all sectors. Railway projects, with a cost escalation of 32.4 per cent, were followed by civil aviation (16.6 per cent) and power (12.5 per cent.) Important sectors to have remained insular to cost escalations were surface transport, with a cost escalation of just 1 per cent, and petroleum refinery products, with an overall cost overrun of a mere 0.3 per cent.

 

Considering value-weighted cost overruns, one can see that the railway projects accounted for almost half of the total cost overruns of all PSU projects. The inclusion of just two more sectors – power and urban transportation – constituted more than 95 per cent of the total cost overrun.

 

Of the 542 projects on the MoSPI monitor, 159 projects were affected by time overruns that ranged from an innocuous one month to a preposterous 12 years. The average time overrun for delayed projects, weighted by the anticipated completion cost, worked out to around 38 months (or more than two and a half years.)

 

The total cost of projects affected by time overruns stood at Rs.75,494 crore, implying that over 35 per cent of the total investment of PSU projects is stymied by time delays.

 

Important sectors where investment is being vitiated by time overruns are power, petroleum refining and railways. In the case of power, 47.5 per cent of the investment was plagued by time overruns. The remaining two industries had respective shares of 43.7 per cent and 37.9 per cent.