Illustrative image – not actual.The Tillari irrigation corporation is likely to commission the Tillari irrigation project in Goa by December 2013.
The project will bring under irrigation 14,521 ha of land in the three talukas of Pernem, Bicholim and Bardez. It is estimated to cost Rs 1,612.15 crore.
Bardez taluka has an irrigation potential of 5,137 ha that will irrigate 30 villages after the canal becomes operational.
When completed, the project is expected to irrigate 5,130 ha in Bicholim taluka, spread over 18 villages. 797 ha has already been irrigated in Bicholim. Also, 4,254 ha is expected to be irrigated in 16 villages of Pernem, where 651 ha has already been brought under irrigation.
The Tillari irrigation project has two main canals, the right bank main canal (RBMC) extending from Tillari to Pernem and the left bank main canal (LBMC) extending from Tillari to Bardez. The RBMC has seven distributaries and almost all are complete. The LBMC has nine distributaries, of which six are complete and work on three is currently in progress. These are expected to be completed by December 2013.
Besides, the corporation has also formed 40 water resource societies in all three talukas. Out of these, five societies have already been handed to the members.