ThyssenKrupp wins order from Coastal EnergenIllustrative image – not actual.

ThyssenKrupp has secured a Rs 275 crore contract from Coastal Energen for coal handling plant at its 1,200 MW Mutiara thermal power plant near Tuticorin in Tamil Nadu.

The Rs 5,000-crore 2x600 MW plant is slated to be completed by the middle of 2012.

Work on the project has started and Harbin Power Engineering is to supply equipment worth about Rs 2,000 crore. The company has completed the basic design and the first shipment is expected by 10 April 2010. Meanwhile, an order for civil works and Bi Flue Chimney has been placed on Gammon India valued at Rs 450 crore and construction is in underway.