Illustrative image – not actual.Kandla Port Trust has shortlisted three bidders for the development of the new container terminal at the port. The three companies -- ABG Heavy Industries, Afcons India and Gammon India -- have been asked to submit their final bids by 22 March 2005.
The Rs.200 crore project involves conversion of Berths No.11 and 12 into dedicated container terminals on BOT basis. The quay length of the terminal would be 545m with backup area of 40 ha.
The project will be awarded on a minimum throughput guarantee and revenue-sharing modes.
KPT has targeted movement of 1.75 lakh TEUs of container traffic in the first year, going up to 3 lakh TEUs in the fifth. Traffic could even increase up to 5 lakh TEUs with the installation of two rail mounted gantry cranes in future.
The project cost is likely to increase to Rs.300 crore, once development of the backup area of 40 ha progresses.