Three in fray for North-Eastern UMTPIllustrative image – not actual.

Three private sector power companies are reportedly in fray for the first ultra mega transmission project (UMTP) for the North-Eastern region in India as five companies backed out from the final bidding round.

Reliance Power Transmission, Sterlite Energy and Lanco Infratech have submitted their final bids to East-North Interconnection Company, a wholly-owned subsidiary of PFC. The financial bids are slated to be opened on 29 September 2009.

The proposed UMTP envisages laying of 427 km of transmission lines, connecting the North and Eastern regions of India to evacuate about 1,700 MW of surplus power. It is expected to be implemented on BOOM basis and is to be awarded through competitive tariff based bidding.

The Union Government is planning to award three UMTP projects - Talcher Augmentation Transmission System (Talcher-II), North Karanpura Transmission System and East-North Interconnection System, with an estimated investment of over Rs 5,500 crore.

The North-East Interconnection UMTP is expected to have two lines, a 217 km long 400 kV transmission line between Bongaigaon in Assam to Siliguri in West Bengal and another 210 km similar line between Purnia and Biharsharif in Bihar. The project is to be completed within three years of awarding the project, with a scheduled commissioning by October 2012.

Of the eight qualified bidders who were short listed in May 2009, only three companies submitted the RFPs. The five companies who did not submit their bids are L&T, Essar Power, CESC, Jindal Steel & Power and JSW Energy.