Illustrative image – not actual.The Noida Metro Rail Corporation (NMRC) has finally got three bidders it needs to go through with the process to pick a company that will build Phase-I of the Aqua Line extension from Noida to Greater Noida in Uttar Pradesh.
This was the fourth time it floated bids since it was unable to find minimum number of applicants needed to go through with the process.
The 14.95 km Aqua Line Corridor from Noida Sector 51 to Knowledge Park V in Greater Noida will have nine stations in total. The estimated cost is Rs 2,294 crore. Phase-I of the corridor is 9.6 km long and will have five stations at sectors 122, 123, Greater Noida Sector 4, Ecotech 12 and Greater Noida Sector 2. Phase-I cost is Rs 563.04 crore, and its deadline is 24 months from the date of approval.
The tenders for construction of Phase-I of the project were opened on 30 June 2021 and the three bidders are--GR Infra Projects, Sam India Builtwell and Ashoka Buildcon. NMRC will announce the final candidate in three weeks after technical assessment of the bids.
NMRC had cancelled the third round of the civil tendering process in February 2021 because of a lack of wide participation from construction companies. It invited fresh tenders on 31 May 2021 that were opened on 30 June 2021.
NMRC first invited tenders in May 2020 and received bids from three firms. One of them was not a construction company. This led to cancellation of the tender in July 2020. The corporation re-invited tenders in September 2020. It received two bids from Sam India and GR Infra Projects in mid-November 2020, but cancelled the same in November-end 2020.
The third round was floated in December 2020 and cancelled in February 2021. Work on the extension of Aqua Line will start in 2021. Work on the Greater Noida Corridor (Sector 51 to Knowledge Park 5) will be executed first before two other extensions are built.
This was the fourth time it floated bids since it was unable to find minimum number of applicants needed to go through with the process.
The 14.95 km Aqua Line Corridor from Noida Sector 51 to Knowledge Park V in Greater Noida will have nine stations in total. The estimated cost is Rs 2,294 crore. Phase-I of the corridor is 9.6 km long and will have five stations at sectors 122, 123, Greater Noida Sector 4, Ecotech 12 and Greater Noida Sector 2. Phase-I cost is Rs 563.04 crore, and its deadline is 24 months from the date of approval.
The tenders for construction of Phase-I of the project were opened on 30 June 2021 and the three bidders are--GR Infra Projects, Sam India Builtwell and Ashoka Buildcon. NMRC will announce the final candidate in three weeks after technical assessment of the bids.
NMRC had cancelled the third round of the civil tendering process in February 2021 because of a lack of wide participation from construction companies. It invited fresh tenders on 31 May 2021 that were opened on 30 June 2021.
NMRC first invited tenders in May 2020 and received bids from three firms. One of them was not a construction company. This led to cancellation of the tender in July 2020. The corporation re-invited tenders in September 2020. It received two bids from Sam India and GR Infra Projects in mid-November 2020, but cancelled the same in November-end 2020.
The third round was floated in December 2020 and cancelled in February 2021. Work on the extension of Aqua Line will start in 2021. Work on the Greater Noida Corridor (Sector 51 to Knowledge Park 5) will be executed first before two other extensions are built.