Thirumangalam flyover to be opened in September 2013Illustrative image – not actual.

The Thirumangalam flyover is likely to open by September 2013.

 

The 737m long flyover on Inner Ring Road will go over the junction of Anna Nagar 2nd Avenue and Mogappair Road, and will speed up travel for commuters from Koyambedu, Ambattur, Red Hills and Avadi. It has four lanes and it will carry traffic in both directions. Each direction will be 7.5m wide with service lanes.

 

The flyover has two abutments and 19 piers which have been completed. Five decks are yet to be constructed.



The total cost of the project is around Rs 61 crore, which includes Rs 19 crore for land acquisition.

 

Earlier, completion scheduled for the project was April 2013, but the project has been delayed by three months due to land acquisition and lack of cooperation between government agencies.

 