Illustrative image – not actual.Thirteen Indian and foreign firms have submitted expressions of interest (EoIs) for implementing the 1,760 km long Central India Pipeline project on build, own, operate and transfer basis. These EoIs are expected to be pre-qualified by the end of September 2001 and the final bids are likely to be called for in November 2001.
The 13 companies that have submitted
EoIs are GVK Industries Ltd, Hyderabad; Bharat Petroleum Corporation Ltd,
Mumbai; Dodsal Ltd, Mumbai; Monroe Stallion Automotive Pvt Ltd, New Delhi; Aban
Construction Pvt Ltd, Chennai; Gammon India Ltd, Mumbai; Indian Oil Corporation
Ltd, Noida; Reliance Petroleum Ltd, Mumbai; VOMSI India Pvt Ltd, New Delhi;
Larsen & Toubro, Chennai; IBRCL Infrastructure and Projects Ltd, Hyderabad;
Transneft, Russia; Sun Securities Ltd, in consortium with OAO Stroylransgaz,
Russia and OAO Gazprom, Russia.
As per government guidelines, only
those firms investing more than Rs.2,000 crore in the refining or oil
infrastructure sector would be eligible for the lucrative marketing of
automobile fuel in the country after the dismantling of the administered
pricing mechanism in the petroleum sector after 31 March 2002. Therefore, the company implementing the
pipeline project will be automatically eligible for the marketing of auto fuel
in India after 31 March 2002.
The project is being implemented by Petronet India Ltd, through its joint venture company, Petronet Central India Ltd, which was incorporated in December 2000.
Petronet Central India Ltd: Equity Structure
|
|
|
Company |
Equity
(%) |
|
Petronet
India |
26 |
|
Indian
Oil Corpn. |
26 |
|
Reliance
Petroleum |
26 |
|
BPCL |
11 |
|
Essar Oil |
11 |
Total |
100 |
The project is proposed to be implemented
in two phases. The first phase, costing Rs.2,221 crore, entails laying a 1,458
km long pipeline originating from Vadinar in Gujarat and terminating at Kota /
Nagpur, installation of pumping stations at Vadinar, Sikka, Koyali and Ratlam
and delivery stations at Rajkot, Indore and Itarsi. Ratlam and Koyali would
also be provided with delivery facilities. Terminal facilities would be
provided at Kota and Nagpur.
In the second phase, the pipeline
would be extended from Kota to Gwalior by laying a 302 km long pipeline.
Pumping facilities at Vadinar, Sikka, Koyali and Ratlam would be augmented and
additional pumping facilities would be provided at Itarsi and Kota.