A tunnel-boring machine (TBM), which started excavation from the Swargate underground Metro station site, has arrived at the Mandai station site and will continue digging a tunnel till the Budhwar Peth station site in Kasba Peth for Pimpri Chinchwad Municipal Corporation (PCMC)-Swargate Metro Corridor.
The Maharashtra Metro Rail Corporation (MahaMetro), which is executing the project in Pune and Pimpri Chinchwad is working on a plan to proceed with tunnelling work between Budhwar Peth and Mandai stations. As per the earlier plan, three machines were to meet at the Mandai station site, wherefrom they were to be extracted.
MahaMetro is in the process of rescheduling the remaining excavation work. The machines will now mostly be extracted at the Budhwar Peth station.
Two machines are excavating a tunnel from Civil Court to Budhwar Peth. Of these, one has already reached the Budhwar Peth station site, while the other is expected to get there by next week.
Two parallel tunnels are being excavated in the underground section, one each for the up and down lines. The excavation of tunnels has been completed in the Agriculture College-Civil Court-Budhwar Peth stretch, while tunnelling is underway in the Budhwar Peth to Swargate stretch.
A fourth machine will not be required -- as was originally planned as three TBMs were enough to complete the work in the stipulated timeframe.
Earlier, MahaMetro had planned to use four TBMs for the underground tunnelling work. The underground section is part of the Pimpri Chinchwad Municipal Corporation (PCMC)-Swargate Metro Corridor. The Metro will run on a viaduct from PCMC to Range Hills, after which it will go underground at the Agriculture College depot. From there, it will run underground till Swargate.