Illustrative image – not actual.The third unit of the 6 x 150 MW Srisailam
Left Bank Hydro project was commissioned in Andhra Pradesh. The unit was synchronised
with the state grid on 21 April 2002. Thus, 450 MW capacity of the plant has
been completed till date. The remaining three units are expected to be progressively
commissioned at intervals of five months, between October 2002 and October 2003.
The project being implemented by
Andhra Pradesh Power Generation Corporation (APGenco) is the first underground
hydel project in South India.
Though the project was sanctioned
in 1986, work commenced only in 1996 after the Japanese Bank for International
Cooperation (JBIC) sanctioned the required loan and had approved direct
payments to the equipment suppliers.
The time overrun has resulted in
steep escalation in the project cost. The Planning Commission had approved the
project cost of Rs.1,166.66 crore in 1991 which has now trebled to Rs.3,432
crore including the interest during construction (IDC) of Rs.950 crore.