Third 150 MW unit of Srisailam Left Bank Hydel commissioned in Andhra PradeshIllustrative image – not actual.

The third unit of the 6 x 150 MW Srisailam Left Bank Hydro project was commissioned in Andhra Pradesh. The unit was synchronised with the state grid on 21 April 2002. Thus, 450 MW capacity of the plant has been completed till date. The remaining three units are expected to be progressively commissioned at intervals of five months, between October 2002 and October 2003.

 

The project being implemented by Andhra Pradesh Power Generation Corporation (APGenco) is the first underground hydel project in South India.

 

Though the project was sanctioned in 1986, work commenced only in 1996 after the Japanese Bank for International Cooperation (JBIC) sanctioned the required loan and had approved direct payments to the equipment suppliers.

 

The time overrun has resulted in steep escalation in the project cost. The Planning Commission had approved the project cost of Rs.1,166.66 crore in 1991 which has now trebled to Rs.3,432 crore including the interest during construction (IDC) of Rs.950 crore.

← All latest storiesBack to top →