Thermax secures EPC order for a captive power plantIllustrative image – not actual.

Thermax has secured EPC order for setting up a captive power plant for its new three million tpa integrated steel plant in Central India.

The company has secured order worth Rs 503 crore. Thermax will design, engineer, construct and commission the project on a turnkey basis. The supply of equipment includes 3 - 160 tonne per hour capacity (3x160 TPH) boilers that use multiple fuels - blast furnace and coke oven gas from the steel process and light diesel oil and two 40 MW each steam turbines. Steam from the boilers will be used to blow air into the blast furnace and to generate 80 MW of power. The order also includes water demineraliser plant, cooling water system, air conditioning and ventilation system, compressed air system, fire fighting facilities, emergency DG set, etc. This project is designed as a zero discharge plant and an effluent treatment plant based on reverse osmosis will recycle water.
 