Illustrative image – not actual.Thermax bagged an order worth Rs.450 crore for setting up a 60 MW captive power plant from an integrated steel unit in Andhra Pradesh. The plant will use process gases and blended coal as fuel.
The scope of the order includes supply and commissioning of boilers and turbines, fuel and ash handling system, civil works, water treatment plant, pollution control system, storage reservoirs and balance of plant equipment. The captive power plant will support the integrated steel project of 1.25 million tpa expandable to 2.5 million tpa capacity.