Illustrative image – not actual.The Madhya Pradesh Power Trading Company (MPPTCL) which plans to set up a 1,200 MW thermal power plant in Shahpura area in Jabalpur has been surrounded by uncertainties due to coal linkages issues.
MPPTCL intends to set up the proposed power project with the help of private investors. Some investors had evinced interest in the power project. Since, MPPTCL has not been able to get a coal linkage from the Union Government within the stipulated time of two years, the investors have withdrawn from the project.
Madhya Pradesh was to get the entire electricity from the project. The Madhya Pradesh Government had made MPPTCL, the nodal agency to facilitate setting up of the project with the help of private player to increase the power availability in the state.
MPPTCL had got environment clearance and identified the vacant government land for the project.
However, MPPTCL is still hopeful of the project and it is exploring other ways to set up the project.