The MMRDA may have to drop its plans to construct second monorail line connecting Thane-Bhiwandi-Kalyan as a report by consultant RITES revealed that the MMRDA will be able to earn just Rs 209 crore every year against its investment of Rs 4,233 crore for the project.

In its viability report, RITES has showed that the project, once ready, will need a viability gap fund to the tune of 90 per cent of its project cost - Rs 4,233 crore. It is expected to take nearly Rs 124 crore every year to run the project; while the income generated through ridership will be only Rs190 crore from tickets and Rs19 crore from advertising revenues.

The MMRDA was planning to construct the 30-km Thane-Bhiwandi-Kalyan monorail on PPP basis. It was slated to be completed by 2015.

Now, the Authority is mulling to take up a 11-km Bhiwandi-Kalyan monorail line.