Thane-Diva rail project to be commissioned by March 2022Illustrative image – not actual.
All civil works on the most delayed Thane-Diva rail project has been completed and the line is expected to be finally commissioned before March 2022.  
 
The next big task is to link rail tracks on both sides for which the Mumbai Railway Vikas Corporation will need to coordinate with the Central Railway. 
 
The completion of this nine km corridor, marred first due to encroachments and later technical glitches, will see a sea-change in the Central Railway’s rail traffic and lead not only an increase in suburban trains but also segregate the outstation trains between Kalyan and Kurla. 
 
The fast local trains will then get a dedicated path. At present, there are six lines between Kalyan and Diva and Kurla Lokmanya Tilak Terminus and Thane.
 
However, there are only four lines between Thane and Diva, which leads to congestion due to crossing of outstation trains. 
 
Due to the COVID-19 pandemic supply chains were delayed and most of the labour went back home. Most of the civil work on the Thane-Diva line is now complete and the process of linking rail tracks will soon begin. 
 
The MRVC is spearheading the project. Once the track linking is completed, the trials of the commissioner of railway safety will happen and once the certifications are in, the line will be commissioned. 
 
The project will help the Central Railway add around 100 more local services as Diva-Thane is the busiest corridor at present. 
 
The deadline for the project, sanctioned in 2008, was December 2015, which was revised to December 2017, then to March 2019, June 2020 and now March 2022. 
 
The cost of the project has escalated from about Rs 130 crore to Rs 440 crore.