The segregation of fifth and sixth lines between Thane and Diva on the Central Railway's Mumbai network has now been completed, allowing for complete segregation of suburban and local-distance trains.
The new railway line involved building of a 1.4 km long rail flyover, three major and 21 minor bridges as well as a 170 mtr tunnel.
After the commissioning of the new railway lines, fast suburban trains will go parallel to existing slow lines via Kalva and Mumbra stations. The tunnel route will be used only for outstation trains. The separation of the corridor will help improve not only the punctuality of trains but also allow the railway authorities to introduce additional suburban trains.
The work on the fifth and sixth lines between Thane and Diva was sanctioned in 2008-09 under the Mumbai Urban Transport Project Phase 2, with equal cost-sharing by the Railway Ministry and the Maharashtra government.
The railway project witnessed both time and cost overruns. As per the original schedule, the project was to be completed in December 2015 at a cost of Rs 130 crore. The cost increased to Rs 440 crore because the railways had to acquire 12,962 sq mtr of land and rehabilitate 469 project affected people.