The Thammanam-Pullepady Road development project, crucial for improving east-west connectivity in Kochi, is progressing as the Revenue Department has handed over acquired land to the Public Works Department (PWD).
A social impact assessment (SIA) for the project is scheduled to begin next month. Following a project review meeting led by Mayor M Anil Kumar and District Collector NSK Umesh, officials confirmed that the remaining land acquisition will be completed within a week. The notification will be issued in April, with the entire acquisition process expected to conclude by June.
The Kerala Infrastructure Investment Fund Board (KIIFB) has allocated Rs 150 crore for land acquisition. A detailed project report (DPR) has already been approved, outlining plans to expand the existing 3.68 km road into a four-lane corridor, linking MG Road and NH Bypass. A total station survey has also been completed in preparation for the works.
Over the past two decades, 84 landowners voluntarily surrendered 163 acres in Ernakulam and Poonithura villages for road development, in addition to the 54 acres acquired from 45 landowners by the civic body. The Kerala Road Fund Board (KRFB) has been tasked with executing the project. Once completed, the upgraded road is expected to significantly ease traffic flow and improve urban connectivity in Kochi.