The South East Central (SEC) Railway has floated a tender for the execution of work for the construction of overpass on the existing main line and the proposed third line between Darekasa-Salekasa station of Nagpur Division.

The contract is to be executed in a timeline of 24 months, at an estimated cost of Rs 220.56 crore.

The work involves the construction of overpass of 100 mtrs. length at ch 56430 on existing DN main line, an overpass of 50 mtrs. length each at ch 57100 & 58300 on existing UP main line & DN main line, underpass of size 2x 5.0 mtrs. at ch 57360, viaduct of 14x 30.50 mtrs. span from ch 56570 to ch 57015 in Maharashtra.

It also includes chain link fencing throughout forest area by the side of existing UP & DN main line, and other miscellaneous work in connection with the third line.

The closing date for bid submission is 06 October, 2023.