Illustrative image – not actual.The government of Telangana is set to increase its power generation capacity from 14,200 MW to 15,000 MW by March 2018 and to about 17,000 MW by the end of 2018.
The capacity augmentation will come through commissioning of 800 MW coal-fired thermal power plant at Kothagudam by March 2018, whose boiler light-up has been completed earlier in February 2018.
Additional capacity will come from 1,080 MW Bhadradri power plant and other sources, including renewables.
The government has set a target of achieving 28,000 MW over the next three to four years.
Of the proposed upcoming capacity, about 4,000 MW is expected to come up at Yadadri power plant, where works are underway. Two units of Bhadradri project are likely to be commissioned by December 2018.
The state plans to have 5,000 MW of solar capacity within a couple of years.