Tehri power project: Stage I targeted for December 2006Illustrative image – not actual.

Tehri Hydro Development Corporation has targeted to fully commission Stage I of 1,000 MW of the Tehri hydropower project in Uttaranchal by December 2006.

Discussing the current project status with ProjectsToday, THDC officials said that Unit No.3 has attained mechanical completion and will be commissioned by September 2006. Unit No.2 and Unit No.1, each of 250 MW, will be commissioned in October and December 2006, respectively, culminating in the overall completion of Stage I.

One unit (No.4) of 250 MW began commercial operations in July 2006. This unit is targeted to produce 1,161 million kwh of electricity during 2006-07.

The Tehri Hydropower complex will be implemented in three stages. The first stage comprises of the Tehri Dam and four power units of 250 MW each. The 260.5m tall earth and rock-fill dam is incidentally the highest in Asia and the third highest in the world. The approved cost of Stage I is Rs.6,621 crore.

Stage II envisages the 400 MW Koteshwar hydropower project that is currently under execution with likely completion by March 2008.

Stage III involves the 1,000 MW Tehri pumped storage plant on which essential works -- head race tunnels and intakes -- have already been completed concurrently with Stage I. This stage is scheduled for completion during 2010-11.

The 2,400 MW Tehri hydropower complex, estimated to cost around Rs.9,600 crore, is expected to generate 6,200 million kwh of power on full commissioning. An estimated 2.70 lakh ha of additional land would be irrigated, besides providing stability of water supply to 6.04 lakh ha of existing land.