Illustrative image – not actual.National Hydro-electric Power Corporation's (NHPC) 510 MW Teesta Stage V hydel power project in Sikkim achieved its first breakthrough.
A 473 metre diversion tunnel with a
12.2 metre diameter, claimed to be NHPC’s longest till date, was completed on
28 June 2001, three months ahead of schedule. Work on another 610 metre tunnel
is going on in full swing and is expected to be completed by September 2002 on
schedule. Once both the tunnels are in place, the Teesta river waters would be diverted
to these tunnels to enable NHPC to start work on the dam, which will be 45
metres high from the riverbed and 90 metres from the deepest foundation.
The project is targeted to be completed
by February 2007 and NHPC is hopeful of completing it by then.