TEECL plans USD one billion investment in data centersIllustrative image – not actual.

Power infrastructure major Techno Electric and Engineering Company (TEECL) is planning to invest USD one billion (about Rs 7,310 crore) in setting up data centres across key Indian cities.

The Kolkata-based listed company with more than 400 completed engineering procurement and construction (EPC) projects is looking to develop data centres backed by green energy.

The company has finalised a plan to develop 250 MW of data centres across India over the next five years. The company is targeting Mumbai Metropolitan Region (MMR), Hyderabad, Pune, National Capital Region (NCR), Chennai and Kolkata for setting up data centres.

For its first project, which is coming up in Chennai, the company has acquired a four acre land parcel from the Tamil Nadu government at SIPCOT IT Park in the city’s southern suburb of Siruseri.

The company is investing about Rs 1,200 crore to develop this data centre with a total load capacity of 45-60 MW, and preliminary site activities for this development have started.

The second project in Kolkata will also be of almost the same size as that of the Chennai data centre and will be developed on nearly five acres with an investment of about Rs 1,200 crore. Both Chennai and Kolkata data centre projects will comprise around USD 340 million or one-third of the total planned USD one billion investment.

The company may opt for leverage 60-40 with debt-equity composition, and it is also open to divesting equity in these projects.

The Chennai project will be 100 percent carbon-neutral as the company has 111 MW of wind energy assets in Tamil Nadu that will be used to fuel the data centre there. The company has also acquired two 10 MW biomass energy plants in Kolkata that will be feeding power to the data centre in the eastern city and this will also be 100 percent renewable.

TEECL’s third data centre, in Hyderabad, will be developed over a larger parcel of land than in Chennai and Kolkata. It may go up to 50 MW and will be completely powered by the company’s captive solar power infrastructure in Hyderabad. The company’s fourth project will be in either Navi Mumbai, Pune or Noida. It has engaged a consultant to study and survey these markets.

 