Illustrative image – not actual.ONGC Petro-additions is likely to sign a technology agreement for the polyethylene and polypropylene plants at the Dahej Petrochemicals Hub in Gujarat by end-September 2009.
Around seven companies had expressed interest in the estimated $40-60 million (approx Rs 196-294 crore) product technology selection process and the bids submitted by them will be scrutinised soon. Of the companies that had submitted bids, two each were from South Korea, Japan and Europe and one was from the US.
Meanwhile, the construction of the Dual Feed Cracker Unit, by the Linde-Samsung consortium at a cost of $1.43 billion (approx Rs 7,007 crore), was progressing on schedule. The infrastructure work being undertaken by IVRCL at a cost of $167 million (approx Rs 818.3 crore), was nearly 70 per cent complete.
The entire work on 507 ha in the Dahej Petroleum, Chemical and Petrochemical Investment Region was expected to be completed by 2012.