Techno Electric arm commissions wind power plant in Tamil NaduIllustrative image – not actual.

Simran Wind Project, a subsidiary of Techno Electric & Engineering Company (TEECL), has fully commissioned its Phase I expansion of 101.4 MW wind power project in Tamil Nadu.


With the completion of the Phase I, TEECL plans to raise its power generation capacity by another 12.6 MW under Part 2 of the Phase I by October 2011. This will take the total power generation capacity of Phase I to 114 MW. The Company has signed a 20 year PPA under REC scheme with the Tamil Nadu Generation & Distribution Company.


The project was funded through a mix of debt (Rs 360 crore) and equity (Rs 240 crore). The project brought in IFC as an equity partner in Simran, extending $5 million (Rs 22.5 crore) for a 3.38 per cent stake. Lenders to the project include IFC, Standard Chartered Bank and DBS Bank.