Tata Steel to raise funds for Kalinganagar project Illustrative image – not actual.

Tata Steel is planning to raise funds for its upcoming new steel project at Kalinganagar, Jajpur district of Orissa.

The company will raise up to Rs 13,000 crore by August 2013 for the phase I of its upcoming six million tonne new integrated steel plant. The company is in advanced stage for achieving financial closure soon. In Phase I it will be funding around Rs 12,000 crore to Rs 13,000 crore on debt and then, after completing (phase-I), will be taking a call on (fund raising for) Phase-II of the project.

The project estimated to cost of about Rs 35,000 crore is coming up in two phases with three million tpa each.  The project is being funded through 50:50 debt-equity ratio. Tata Steel is in possession of 1,700 acre at present against a total requirement of over 5,000 acre for the full six million tpa capacity.