Illustrative image – not actual.Tata Steel's three greenfield projects have witnessed a cost escalation of over 50 per cent (nearly Rs.35,000 crore), according to a recent report of global financial firm Credit Suisse. The three projects coming up in Jharkhand, Orissa and Chhattisgarh have been delayed by 2-3 years due to land acquisition problems.
However, the capex at current prices for the Jharkhand plant is much higher, therefore, it is estimated that the cost overrun in the project is likely to be more than 50 per cent. The Jharkhand and Chhattisgarh projects, which were to be completed by 2012 and 2015, respectively, have been delayed by 36 months while the Orissa project has been delayed by 24 months from the deadline in 2013.
With the delays, the total expenditure will escalate to over Rs.1,00,000 crore as the construction cost shot up to $1,000 a tpa from $600 a tpa when the company announced the projects. Surging steel prices, equipment and construction costs and land value are the key reasons for the escalation of expenditure.
The steel projects of ArcelorMittal in Jharkhand and Orissa have also been delayed by 2-3 years due to land acquisition delays, which pushed its capital cost by 50 per cent.
Also See: