Tata Steel plans jetty at HaldiaIllustrative image – not actual.

Tata Steel is planning to develop captive riverine jetty at Haldia in West Bengal with an estimated investment of Rs.100 crore.

The proposed jetty will primarily handle clean cargo and have the final capacity of two million tpa. It will also include an open back up storage space of 15 acres with a railway siding of 800 metre along with two mobile harbour cranes.

A concession agreement regarding the purpose is likely to be signed by May 2008. Work on the jetty and development of backup facilities is likely to commence by September 2008 and is scheduled for completion by August 2009.