Illustrative image – not actual.Tata Steel is planning to construct a new vacuum induction melting (VIM) furnace at its South Yorkshire plant in the UK.
For the purpose, the company is planning to invest £15 million (approx Rs 149.28 crore). Tata Speciality Steels will work with German metallurgical technology company SMS Mevac, a supplier of vacuum steelmaking equipment, to build the VIM facility. The company expects to operationalise the facility by 2015.
VIM production involves melting and casting steel in an oxygen-free atmosphere, producing steel which is very clean with low gas content.
Meanwhile, the company is also mulling setting up a power station at its Port Talbot works in Wales, UK, to replace old equipment. The gas-fuelled power station is likely to take three years to build and is due to have a lifespan of 35 years. Tata Steel has already submitted a proposal to Neath Port Talbot Council for approval.
Further, the company is also planning to install two boilers and two steam turbines connected to the existing blast furnace gas distribution network in order to receive gas through the pipe work. It intends to increase its power generation capacity at Port Talbot from 115.7 MW to 225 MW.