Illustrative image – not actual.Tata Steel’s Rs.1,770 crore project of
expanding its crude steel capacity by 1 million tpa is on track with major
orders placed.
The company has awarded a Rs.235 crore
turnkey contract to a consortium led by Larsen & Toubro for constructing a
2.3 million tpa sinter plant at Tata Steel’s Jamshedpur Steel Complex. The
sinter plant is a vital component of the company’s brownfield expansion
project.
Outokumpu-Lurgi Metallurgie, the German
steel major and world leader in sintering technology, joins L & T in the
consortium.
L&T’s share in the contract is
Rs.158 crore comprising main package, civil, structural and auxiliary work.
Lurgi’s portion is valued at €13.68 million (around Rs.60 crore). The sinter
plant project has a very tight schedule of 17 months – from basic engineering
to commissioning.
It may be mentioned that Tata Steel’s
project was earlier estimated to cost Rs.1,995 crore. The reduction has come
about due to lower cost of balancing equipment. Apart from the sinter plant,
other important components the project include enhancing capacity of the
G-Blast furnace to produce 60,000 tpa of hot metal, and installation of a
Rs.400 crore rebar mill to augment the capacity of downstream products.
To support the crude steel expansion,
Tata Steel is having BOC India construct an industrial gases plant at the
Jamshedpur Complex. This would be the third such by BOC India -- two plants
with capacities of 1290 tpd and 220 tpd – are already operational.
Meanwhile, Tata Steel has placed
another Rs.80 crore order for rebuilding one of its blast furnaces. SMS Demag
of Germany would provide technology for the revamped furnace. A critical
shutdown of just 85 days is targeted.
It may be recalled that in May 2002, L & T had modernized the “F”
Blast Furnace with a record shutdown period of only 105 days.